Interstate 5 Carpool Lane from Rte 134 to Rte 170

Description: In Los Angeles County on Rte 5 from Rte 134 to Rte 170. Construct one HOV lane in each direction.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Burbank, Glendale, Los Angeles
Zip Code 90027, 91201, 91331, 91352, 91502, 91504
 
Senate District
17, 20, 21
Assembly District 38, 39, 43
Congressional District 27, 28, 29
 
Caltrans District
07
 
 
County/State Route Los Angeles 5
Postmile Begin/End 26.7 36.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  16756      
Lane Miles Added (HOV)  19.4    9.6  
Peak Period Time Savings (minutes)  1223200      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Nancy Pe 213-897-0208   nancy.n.pe@dot.ca.gov
Design (PS&E) Phase
Caltrans Nancy Pe 213-897-0208   nancy.n.pe@dot.ca.gov
Right of Way Phase
Caltrans Nancy Pe 213-897-0208   nancy.n.pe@dot.ca.gov
Construction Phase
Caltrans Nancy Pe 213-897-0208   nancy.n.pe@dot.ca.gov
 
Corridor System Management Plan
Caltrans Nancy Pe 213-897-0208   nancy.n.pe@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $0 $0
CMIA
$73,000 $-8,287 $64,713
SLPP
$0 $13,061 $13,061
Non-bond Funding
State/Federal*
$153,158 $97,451 $250,609
Local**
$130,780 $292,906 $423,686
Non Budgeted ETC
$0 $0 $0
 
Total**** $356,938 $395,131 $752,069

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $4,378 $4,378 $3,644
Design(PS&E)
$20,000 $62,408 $82,408 $80,728
Right of Way
$26,700 $63,784 $90,484 $80,858
Construction
$310,238 $264,561 $574,799 $544,613
 
Total* $356,938 $395,131 $752,069 $661,389

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
04/03/1998 

12/29/2000 
100  04/03/1998 

12/29/2000 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
12/29/2000 

06/29/2009 
100  12/29/2000 

06/29/2009 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
12/17/2001 

06/25/2009 
84  12/17/2001 

06/25/2009 


Begin Construction Phase

End Construction Phase
 

 
 

03/01/2016 
12/06/2010 

08/30/2018 
12/06/2010 

06/07/2021 


-34 
Begin Closeout Phase

End Closeout Phase
 

 
04/23/2018 

 
03/30/2017 

10/30/2020 
100  06/10/2021 

01/13/2023 
-51 

-27 
Corridor System Management Plan
Adoption Date     06/01/2009   
Implementation Date     07/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 16756
Lane Miles Added (HOV) 19.4 9.6
Peak Period Time Savings (minutes) 1223200

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.